City of Keystone Heights City Council Meeting, July 13, 2026, 6pm
Title
Geneva Jungle Assessment Presentation
Description

The Geneva Jungle was constructed by a Community Build Event in 1997. Leathers and Associates (L&A) oversaw the design and construction. We recently had L&A assess the facility.

Executive Summary: The playground should be expected to last around 20 years with proper maintenance. The playground is currently 29 years old. The original materials used in the playground were Pressure Treated wood posts and Pressure Treated wood framing with Composite decking. The original wood was treated with CCA* which is no longer allowed on playgrounds. Most of the main support posts are in fair condition. The framing is also in reasonable condition for its age. Some of the equipment has some form of maintenance or safety non-compliance concerns. The playground has lasted 9 more years than projected. Proposed Courses of Action:

  1. A minor renovation (7+ year lifespan extension $66,000, 5 days using the community build model. $9,400/year of usable life.
  2. A major renovation (10+ year lifespan extension) $193,000. 5 days using the community build model. $19,300/year of usable life.
  3. New Build (30 years with minimal maintenance needs). $365,000 6 days. $12,100/year of usable life.

 

Per our Purchasing Policy, L&A will be required to compete in an invitation to bid process.

 

Recommendation

Council motion to proceed with a procurement process for a minor renovation of the playground.

 

POC/Presented by- City Manager- Jamie Booth, Q&A support from Brett Strnad of Leathers and Associates

 

Contact
Jamie Booth, City Manager
Financial Impact
Fiscal Impact- $66K to $365K
Review Comments